• We have completed the physical build of the HA infrastructure.
• We have built the Veeam Hypervisor and are in the process of building the Veeam VM infrastructure.
• We have connected the Veeam backup server to the Vcenter management VLANs on the OLD hypervisors.
• We are expecting the DELL engineer on site to configure the SANS WC /2/17 , in the meantime we are building the Vcenter environment on local storage.
• The firewalls have been configured for local support access.
• There are a number of streams of work in this project, the most immediate is getting the Veeam backup environment established.
...
• Establish and test backup of the OLD system hypervisors (expected WE /2/17).)
• DELL to configure SANs (expected WE 3/3/17 )
• Establish a basic backup of all existing VM’s with RR (expected WE 3/3/17 )
• Aimes to establish RDP server for RR to access infrastructure (expected WE /3/17 )
• Aimes to test restore of VM’s to new infrastructure (expected WE /3/17 )
• Aimes/RR to agree Migration plan (expected WE /3/17 )
• Aimes/RR to test Migration plan (expected WE /3/17 )
• Migration, when RR are happy with the plan of actions
...