- Review outstanding tasks
- Plan any new work for the week
Discussion items
Item | Who | Notes |
---|---|---|
Outstanding tasks | Tim Whitlock (Deactivated) |
|
Moving PV Domain |
| |
3C Extract |
| |
Barts patient data extract |
| |
Penetration testing | Penetration testing. We are still awaiting the N3 report. The internet penetration testing is provisionally booked for the 8th-22nd March. We will need to provide:
| |
Liverpool PV feed issues | Cyberone have been incontact about the PV feed issues from Liverpool however they have not so far sortedtthe issues. George Swinnerton will follow up. |
Action items
- 3C Extract fro Richard Haynes DSA71 George Swinnerton to progress
- Barts data extract of own data George Swinnerton to progress
- Liverpool PV feed issues George Swinnerton to follow up with Cyberone and hopefully resolve the issues