2024-01-15 Meeting notes
Participants
@Joel Collins
@Andrew Atterton
@George Swinnerton
@Marta Badji
@Michael Ruston
@Philip Main
@Retha Steenkamp
@James Medcalf
@Sarah Evans
Discussion Points
Priorities (and things what we did)
Andre
On leave
Reference ranges for PKB
Waiting for final confirmation of last code
PKB Scotland send
Waiting for confirmation to send last 1 unit
Update UKRDC transfer script
On progress
Andy
RADAR 3
Ongoing
Work with Retha to decide NHSBT data retention policy
Can wait
Laptop order
Double check delivery
George
UKRDC testing
INS testing
Final queries for Citrus
PHOSPHATE Extract migration, SIMPLIFIED feed migration
Investigate missing data
Validation Testing
NHSBT - Deletion of Irish Patients
PKB usage data transfer
Waiting for response to George RE encryption
George to chase up
Joel
Schema conversion data storage
Continue. Waiting on schema release 4.2 - Go through with G
Finish testing ACT/Data-Collection
Work with Michael to archive and decommission Nurture and PV TEST servers
Get ACT set up on a new machine
Email Joe first with the list of old and new servers
Continue working through handover todo list
Marta
Start contacting people for data fixes - with Data Team.
Ongoing
Do SQL course
Continuing
PKB queries
Back to chasing up data correction stuff
Michael
New starters
Chase up new licenses
Data Protection Toolkit
NHS SES DCB1596 stuff
InTune on mobile stuff - Planned for
SSL Certs
Validation in progress
Need to email the named trustee
Get new Windows server for ACT installation
Work with Joel on server decommissioning
Phil
CUPID development
Clean up / annotate / test insert code
Decide how to handle sites switching renal systems
Kings EPIC feed
Data model for “work items”
Quarterly Extracts
On hold until new year
Deploy updated schema converter to staging
Investigate errors using files sent by George
Sarah
Working through setup stuff
Go through data correction work with Marta
Go through UKRR Extract work with Phil
Find a Python course (talk to Andy?)