/
2024-02-26 Meeting notes

2024-02-26 Meeting notes

Participants

  • @Joel Collins

  • @Andre Ortega Alban

  • @Andrew Atterton

  • @George Swinnerton

  • @Gleb Rysev

  • @Oliver Reeves

  • @Philip Main

  • @Retha Steenkamp

Priorities (and things what we did)

Andre

  • Reference ranges for PKB

    • Waiting for final confirmation (George) of last code

  • Update UKRDC transfer script

    • Replace the other processes (pv-decrypt-renal, pv-decrypt-diabetes, pv-decrypt-ibd, pv-decrypt-heart, rda-decrypt-rdalive, rda-decrypt-rdastaging) with the new ukrdc-transfer script

  • UKRDC tickets

    • Use the processed data to clean the codes and UoM

  • UKRR RDA extract

  • Update NHSE extract for March

Andy

  • RADAR 3

    • Ongoing

George

This Week

  • UKRDC Feed Testing

  • Investigate CUPID

  • Validation Testing

  • PHOSPHATE Extract migration, SIMPLIFIED feed migration

    • Investigate missing data

Not This Week

  • INS testing

    • Final queries for Citrus

  • NHSBT - Deletion of Irish Patients

  • PKB usage data transfer

    • Waiting for response to George RE encryption

      • George to chase up

Joel

  • Chase up ACT server access

  • Disable healthchecks (Sentry Cron monitoring confirmed working)

    • Fix sentry duplicated notification emails

  • Finish PKB handover

  • Update (and hand over?) UKRDC Dashboard intro presentation

  • Actually start thinking about moving OneDrive somewhere

  • Schema conversion data storage

    • Waiting on schema release 4.2

  • Finish testing ACT/Data-Collection

    • Work with Michael to archive and decommission Nurture and PV TEST servers

    • Get ACT set up on a new machine

  • Continue working through handover todo list

Marta

Leave

  • Data correction - with Data Team and RaDaR Team.

    • Ongoing

  • PKB queries

  • Continue Python course

Michael

Leave

  • Data Protection Toolkit - Ongoing

    • Finish this week

  • NHS SES DCB1596 stuff

  • SSL Certs

    • Put in purchase with Digicert

  • Work with Joel on server decommissioning and upgrades

    • Disk space upgrades in particular

Phil

  • CUPID development (onging)

    • Clean up / annotate / test insert code

      • Decide how to handle sites switching renal systems

        • Kings EPIC feed

    • Plan investigations (workitems) with Joel

  • Quarterly Extracts (ongoing)

    • Provide any support for fixes with ongoing testing sites

  • Schema converter (ongoing)

Sarah

Not in meeting

  • Continue working through Python course.
    Go through data correction work with Marta

  • Go through UKRR Extract work with Phil

  • Working through setup stuff

  • General support/tickets?

Gleb

  • Continue developing consented_cohort

    • Finish profile functionality (i.e., logins/passwords/withdrawals etc.)

    • Start working on databases

    • Resolve github actions issues

Oliver

  • PKB Tickets - with Andre

    • Last one this week

  • RADAR stuff

    • Hopefully starting this week

Misc. Notes

Upgrading postgres on RHEL6 servers

https://www.postgresql.org/download/linux/redhat/

Outstanding Tasks