2018-10-08 Meeting notes

2018-10-08 Meeting notes

Date

Attendees

Arrived later

Apologies

Goals

  • Review Outstanding Tasks
  • Discuss up coming work
  • Identify work for next week

Discussion items

ItemWhoNotes
Outstanding Tasks
  • Release of the QBL blocks code and other fixes is awaiting further feedback from Fran and her testing.Tickets to be included:
 Data Quality ReportsThe DQ reports have bee reviewed by Fran and Retha and it has been decided that some issues should be fixed in the next week or so before the data is finalised. The current reports are those that have been run historically and don't necessarily check everything required any more. Fran is likely to want some form of missing data report to be developed. The DQ reports were run over the last two years files since they weren't run on last years files.
NHS England Extract

George Swinnerton has run the final NHSEngland extract for the 2017 data. He has told them the next extract is likely to be December/January .

Updates
  • The Atlassian tools all need updating and hopefully will e over the next few weeks.
  • There are just two SSL certificates to be renewed before Christmas but currently we have no renewal tokens to do that.

Action items

  • George Swinnerton to identify the problem data fields for which a schema change may be required or decision concerning coding